Financial Reports

Your GO Bond dollars at work. Explore how funds are allocated, spent, and making a difference
across Lauderhill.

RISE Lauderhill logo
$10,877,500
$12,656,850
$6,816,250

Total Budget

Total: ~65,000,000

Monthly Progress Report

1
Bond-Expenditure-Report.pdf Bond Expenditure Report.pdf application/pdf
Download 1.85 MB 2026-07-14 July 14, 2026 2026-07-13 July 13, 2026

5

18ee2eccea

Overall GO Bond Funds Status

0 (0%)

  • Total Spent

    Dollars that have been spent on approved projects.

0 (0%)

  • Open Purchase Orders

    Dollars committed to projects that are in progress.

0 (0%)

  • Remaining Budget Available

    Dollars available for future projects and needs.

RISE Lauderhill logo

Citywide Wall – Beautification

RISE Lauderhill logo

Citywide Wall – Beautification

Pressure Cleaning & Painting of Approximately 12 Miles of City Privacy Walls

Budget

$

Spent

$0

Remaining

$

Completed

Status

In Procurement

Project Timeline

Project Approval

Complete

Procurement

In Progress

In Planning

Upcoming

Design

Upcoming

Build

Upcoming

Close

Upcoming

21st Street and 46th Avenue – Passive Park

Budget

$1,425,000

Spent

$0

Remaining

$1,425,000

Completed

Status

Approved

Project Timeline

Project Approval

Complete

Procurement

Upcoming

In Planning

Upcoming

Build

Upcoming

Close

Upcoming

Wolk Park – Architectural Park Design

Budget

$565,700

Spent

$341,450

Remaining

$3,177,310

Completed

Status

Design

Project Timeline

Project Approval

Complete

Procurement

Complete

In Planning

Complete

Design

In Progress

Build

Upcoming

Close

Upcoming

George Park Court Cover with Column

St. George – Architectural Park Design

Budget

$

Spent

$565,700 

Remaining

$

Completed

Status

Design

Project Timeline

Project Approval

Complete

Procurement

Complete

In Planning

Complete

Design

In Progress

Build

Upcoming

Close

Upcoming

Fire Station 57 – Entrance Plaza Renovations

Budget

$190,000

Spent

$30,877

Remaining

$190,000

Completed

Status

Build

Project Timeline

Project Approval

Complete

Procurement

Complete

In Planning

Complete

Build

In Progress

Close

Upcoming

St. George – Parking Lot Upgrades

Budget

$8,241,250

Spent

$0

Remaining

$7,756,450

Completed

Status

Approved

Project Timeline

Project Approval

Complete

Procurement

Upcoming

In Planning

Upcoming

Build

Upcoming

Close

Upcoming

St. George – Existing Building Enhancement

Budget

$8,241,250

Spent

$0

Remaining

$7,756,450

Completed

Status

Approved

Project Timeline

Project Approval

Complete

Procurement

Upcoming

In Planning

Upcoming

Build

Upcoming

Close

Upcoming

St. George – Multipurpose Artificial Turf Field

Budget

$8,241,250

Spent

$0

Remaining

$7,756,450

Completed

Status

Approved

Project Timeline

Project Approval

Complete

Procurement

Upcoming

In Planning

Upcoming

Build

Upcoming

Close

Upcoming

St. George – Pool Installation

Budget

$8,241,250

Spent

$0

Remaining

$7,756,450

Completed

Status

Approved

Project Timeline

Project Approval

Complete

Procurement

Upcoming

In Planning

Upcoming

Design

Upcoming

Close

Upcoming

Wolk Park – Tennis Court Lighting Project

Budget

$3,562,500

Spent

$43,740

Remaining

$3,177,310

Completed

Status

Build

Project Timeline

Project Approval

Complete

Procurement

Complete

In Planning

Complete

Build

In Progress

Close

Upcoming

Learn more about business opportunities, procurement, and vendor resources available through the City of Lauderhill.

City of Lauderhill's Procurement Page
Scroll to Top