Citywide Building & Facilities Hardening
Project Budget $950,000 Spent $0 Remaining $950,000 Completed Status Approved Project Timeline Project Approval Complete Procurement Upcoming In Planning Upcoming Build Upcoming Close Upcoming

Project Budget $950,000 Spent $0 Remaining $950,000 Completed Status Approved Project Timeline Project Approval Complete Procurement Upcoming In Planning Upcoming Build Upcoming Close Upcoming

Project Budget $9,975,000 Spent $0 Remaining $9,975,000 Completed 1% Status Approved Project Timeline Project Approval Complete Procurement Upcoming In Planning Upcoming Build Upcoming Close Upcoming

Project Budget $171,000 Spent $0 Remaining $171,000 Completed Status Approved Project Timeline Project Approval Complete Procurement Upcoming In Planning Upcoming Build Upcoming Close Upcoming

Project Budget $47,500 Spent $0 Remaining $47,500 Completed Status Procurement Project Timeline Project Approval Complete Procurement In Progress In Planning Upcoming Build Upcoming Close Upcoming

Project Budget $570,000 Spent $0 Remaining $570,000 Completed Status Approved Project Timeline Project Approval Complete Procurement Upcoming In Planning Upcoming Build Upcoming Close Upcoming

Project Budget $5,700,000 Spent $0 Remaining $5,700,000 Completed Status Approved Project Timeline Project Approval Complete Procurement Upcoming In Planning Upcoming Build Upcoming Close Upcoming

Project Contractor Flynn Engineering Back to Project Budget $2,707,500 Spent $94,430 Remaining $2,650,330 Completed Status Design Project Timeline Project Approval Complete Procurement Complete In Planning Complete Design In Progress Build Upcoming Close Upcoming

City of Lauderhill Project Resource Pavement Resurfacing Program Project Budget $7,600,000 Spent $0 Remaining $7,600,000 Completed Status Project Approved Project Timeline Project Approval Complete Procurement Upcoming In Planning Upcoming Build Upcoming Close Upcoming

Project Budget $0 Spent $4,598 Remaining $565,401 Completed Status Complete Project Timeline Project Approval Complete Procurement Complete In Planning Complete Build Complete Close Complete

Project Budget $8,241,250 Spent $0 Remaining $7,756,450 Completed Status Approved Project Timeline Project Approval Complete Procurement Upcoming In Planning Upcoming Design Upcoming Build Upcoming Close Upcoming