Home / East Lauderhill / Lauderhill 6-12

Lauderhill 6-12

Neighborhood Park improvement project within the RISE Lauderhill GO Bond program

Project Summary

Community

East Lauderhill

Total Budget

$1,415,500

Expenditures

$0

Remaining Budget

$1,415,500

Project Description

Lauderhill 6-12 will receive several improvements including:

  • Outdoor bleachers
  • New pavilion
  • Athletic field fencing
  • Athletic field turf grass renovation and irrigation
  • Score board installation
  • Sports lighting installation

Photo Gallery

Project Updates

Lauderhill 6-12 – Sports Lighting

Budget

$522,500

Spent

$0

Remaining

$522,500

Completed

Status

Approved

Project Timeline

Project Approval

Complete

Procurement

Upcoming

In Planning

Upcoming

Build

Upcoming

Close

Upcoming

Lauderhill 6-12 – Score Board

Budget

$19,000

Spent

$0

Remaining

$19,000

Completed

Status

Approved

Project Timeline

Project Approval

Complete

Procurement

Upcoming

In Planning

Upcoming

Build

Upcoming

Close

Upcoming

Lauderhill 6-12 – Athletic Field Turf Grass Renovation

Budget

$570,000

Spent

$0

Remaining

$570,000

Completed

Status

Approved

Project Timeline

Project Approval

Complete

Procurement

Upcoming

In Planning

Upcoming

Build

Upcoming

Close

Upcoming

Lauderhill 6-12 – Athletic Field Fencing

Budget

$47,500

Spent

$0

Remaining

$47,500

Completed

Status

Approved

Project Timeline

Project Approval

Complete

Procurement

Upcoming

In Planning

Upcoming

Build

Upcoming

Close

Upcoming

Lauderhill 6-12 – Pavilion

Budget

$190,000

Spent

$0

Remaining

$190,000

Completed

Status

Approved

Project Timeline

Project Approval

Complete

Procurement

Upcoming

In Planning

Upcoming

Build

Upcoming

Close

Upcoming

Project Life Cycle

Project Approval

Priorities
Identified

Procurement

Contracts
Awarded

In Planning

Scope
Development

Build

Construction
In Progress

Close

Project
Completed

Location

1901 NW 49th Avenue, Lauderhill, FL 33313

Quick Facts

Category:

Parks

Project Type:

Neighborhood Improvement

Estimated Start:

FY 2027

Estimated Completion:

FY 2028

Documents

Scroll to Top